Here are the pictures of the progress along Route 147 from my March 12th flight. They are moving dirt, working on tearing the old bridge down, and
March 12, 2018 Route 15
Here are more pictures from when I was up on March 12. These show the development along Route 15. It seems they are always moving dirt. They are also
February 21, 2018 First Bridge Beams Set
A bumpy ride today with the wind! It was a little warmer than my last flight. I was able to get some good pictures today. They are beginning to set
January 26, 2018 Bridges
Pictures from January 26 shows the work being done on the bridge piers. One of the forms is coming down and the guys are working on rebar on the
January 26, 2018 – Route 147
Here's some pictures of the Route 147 side. They are working on tearing down the old bridge now that traffic was diverted to the new one.
January 26, 2018 Route 15
Here is Route 15 on January 26. You can see that dirt continues to be moved. They are also putting in piping for drainage. The wall continues to be
January 10, 2018 Bridges
Here are some pictures of my January 10th flight. They are working on the bridges. There was still plenty of ice in the river on this cold beautiful
January 10, 2018 Route 15
Here are some pictures from January 10 of the work being done along Route 15. There is a lot of excavating of the ground being done.
January 10, 2018 Route 147
Here are some pictures from my January 10 flight. It was a cold morning but you could see for miles. These pics show the work they are doing along
January 3, 2018 River Bridge
This flight was really COLD. The ice is all the way across the river right now and work has stopped for the time being, but this point of view of the
December 21, 2017 Bridge
Here's some pretty close up shots of the susquehanna river bridge pier construction progress this week. If you look close in a few pictures, you can
December 21, 2017 Route 147
Here's some more pictures from my latest flight on December 21st from the Route 147 side. The road is progressing quite nicely. Winter has clearly
December 21, 2017 Route 15
Here's the last batch of pictures from my December 21st flight. These were all from the Route 15 side.
Winter 2017 Bridge
The new bridge on the 147 side is completed and the crews are nearing completion of the bypass road to move traffic onto it. It was great to see the
Winter flyover of the CSVT – Video
Here's a video from one of my recent flyovers. I started on the Route 147 side in this video and worked across the river to the Route 15 side. You