I was able to get up today but there was not much progress with the holiday. Here are the pictures I got for Routes 15 and 147. Have a great day!!
May 21, 2018 Route 147
Here are some more of my flight. These give you an update for the progress along Route 147.
March 12, 2018 Route 147
Here are the pictures of the progress along Route 147 from my March 12th flight. They are moving dirt, working on tearing the old bridge down, and
January 26, 2018 – Route 147
Here's some pictures of the Route 147 side. They are working on tearing down the old bridge now that traffic was diverted to the new one.
January 10, 2018 Route 147
Here are some pictures from my January 10 flight. It was a cold morning but you could see for miles. These pics show the work they are doing along
December 21, 2017 Bridge
Here's some pretty close up shots of the susquehanna river bridge pier construction progress this week. If you look close in a few pictures, you can
December 21, 2017 Route 147
Here's some more pictures from my latest flight on December 21st from the Route 147 side. The road is progressing quite nicely. Winter has clearly
Winter flyover of the CSVT – Video
Here's a video from one of my recent flyovers. I started on the Route 147 side in this video and worked across the river to the Route 15 side. You
December 5, 2017 Route 147
This was a beautiful fall morning to fly, watching the sun rise over Montour Ridge. There has been more progress on the bridge over Chillisquaque
Late summer 2017 Route 147
The crews are making a lot of head way on Route 147. They have gotten the new overpass in for Acorn Drive as well as the new bridge for the
Summer 2017 Route 147
This was a beautiful summer day to be flying. This time I was able to get some pictures of the piers installed for a bridge. The crews have moved
April 28, 2017 Route 147
Here the crews are continuing to move a lot of ground and working on the new ridge rd layout.
2016-2017 Winter Photos
Here the crews are getting rebar installed for the base of the piers. Also shown are some pictures of the trees that were cleared along route 147 for
October 21, 2016 Photos
Starting to do prep work for the foundation of the piers, still moving dirt on both the route 15 and 147 side of the river. Another beautiful day to
October 15, 2016 Photos
At this point it was mostly earth moving and ground preparation. The causeway was being built in order to begin the work on piers. In this set of